Monday, 8 May 2017

DESIGN OF INTZE WATER TANK AND COST ESTIMATION

INTRODUCTION:

A water tank is used to store water to tide over the daily requirement. In the construction of concrete structure for the storage of water and other liquids the imperviousness of concrete is most essential. The permeability of any uniform and thoroughly compacted concrete of given mix proportions is mainly dependent on water cement ratio .The increase in water cement ratio results in increase in the permeability .The decrease in water cement ratio will therefore be desirable to decrease the permeability, but very much reduced water cement ratio may cause compaction difficulties and prove to be harmful also. Design of liquid retaining structure has to be based on the avoidance of cracking in the concrete having regard to its tensile strength.
Cracks can be prevented by avoiding the use of thick timber shuttering which prevent the easy escape of heat of hydration from the concrete mass. The risk of cracking can also be minimized by reducing the restraints on free expansion or contraction of the structure.                                                                                             
                                                                                  Fig.-Front view of water tank


OBJECTIVES:

(a) To make a study about the analysis and design of water tanks.
(b) To make a study about the guidelines for the design of liquid retaining structure according to IS Code.
(c) To know about the design philosophy for the safe and economical design of water tank.

INTRODUCTION TO SITE:

The project location is situated near the second building of Institute of Technology gopeshwar.
                                                             Fig.-Location of project 
                                             
                                                      Fig.-Location of project


LITERATURE REVIEW:

The most common type of circular tank is the one which is called an INTZE Tank. In such cases, a domed cover is provided at top with a cylindrical and conical wall at bottom. A ring beam will be required to support the domed roof. A ring beam is also provided at the junction of the cylindrical and conical walls. The conical wall and the tank floor are supported on a ring girder which is supported on a number of columns.
Usually a domed floor is shown in fig a result of which the ring girder supported on the columns will be relieved from the horizontal thrusts as the horizontal thrusts of the conical wall and the domed floor act in opposite direction.
Sometimes, a vertical hollow shaft may be provided which may be supported on the domed floor.

WATER TANK:

 DEFINITION:

Circular tanks with flat bottom as well as with domical bottom. In the flat bottom, the thickness and reinforcement is found to be heavy. In the domed bottom, though the thickness and reinforcement in the dome is normal, the reinforcement in the ring beam is excessive. In case of larger diameter tanks, an economical alternative would be to reduce its diameter at its bottom by conical dome, such a tank is known as INTZE tank and is very commonly used.

SOURCES OF WATER SUPPLY:

The various sources of water can be classified into two categories:
I. Surface sources, such as
         a. Ponds and lakes;
         b. Streams and rivers;
         c.  Storage reservoir  
         d. Oceans, generally not used for water supplies, at present.

II. Sub-surface sources or underground sources, such as   
         a.Springs;
         b.Infiltration wells; and
         c.Wells and Tube-wells.

     TYPES OF WATER TANK: 

      1)      Classification based on under three heads: 
          i. Tanks resting on ground
   ii.  Elevated tanks supported on staging
  iii.  Underground tanks.

      2)      Classification based on shapes
    i. Circular tanks
   ii. Rectangular tanks
  iii. Spherical tanks
  iv.  INTZE tanks
   v. Circular tanks with conical bottom

JOINTS IN WATER TANK:

MOVEMENT JOINTS. There are three types of movement joints.
  1. Construction Joint: It is a movement joint with deliberate discontinuity without initial gap between the concrete on either side of the joint. The purpose of this joint is to accommodate construction of the concrete.
  2. Expansion Joint: It is a joint with complete discontinuity in both reinforcing steel and concrete and it is to accommodate either expansion or contraction of the structure. A typical expansion joint.
  3. Sliding Joint: It is a joint with complete discontinuity in both reinforcement and concrete and with special provision to facilitate movement in plane of the joint. This type of joint is provided between wall and floor in some cylindrical tank designs.

       CONTRACTION JOINTS.

                   This type of joint is provided for convenience in construction. Arrangement is made to            achieve subsequent continuity without relative movement. One application of these                joints is between successive lifts in a reservoir wall. 

   
            TEMPORARY JOINTS.
            A gap is sometimes left temporarily between the concrete of adjoining parts of a structure which after a suitable interval and before the structure is put to use, is filled with mortar or concrete completely as with suitable jointing materials. In the 1st case width of the gap should be sufficient to allow the sides to be prepared before filling. 
FACTOR AFFECTING OF WATER TANK 

FACTORS. AFFECTING PER CAPITA DEMAND:

Size of the city: Per capita demand for big cities is generally large as compared to that for smaller towns as big cities have sewered houses.

Presence of industries.

Climatic conditions.

Habits of economic status.

Quality of water: If water is aesthetically $ people and their medically safe, the consumption will increase as people will not resort to private wells, etc.

Pressure in the distribution system.

Efficiency of water works administration: Leaks in water mains and services; and unauthorised use of water can be kept to a minimum by surveys.

Cost of water.

Policy of metering and charging method: Water tax is charged in two different ways: on the basis of meter reading and on the basis of certain fixed monthly rate.

FLUCTUATIONS IN RATE OF DEMAND:

 Average Daily per Capita Demand = Quantity Required in 12 Months/ (365 x Population)
If this average demand is supplied at all the times, it will not be sufficient to meet the fluctuations.

Seasonal variation: The demand peaks during summer. Firebreak outs are generally more in summer, increasing demand. So, there is seasonal variation.

Daily variation depends on the activity. People draw out more water on Sundays and Festival days, thus increasing demand on these days.

Hourly variations are very important as they have a wide range. During active household working hours. i.e. from six to ten in the morning and four to eight in the evening, the bulk of the daily requirement is taken. During other hours. The requirement is negligible. Moreover, if a fire breaks out, a huge quantity of water is required to be supplied during short duration, necessitating the need for a maximum rate of hourly supply.
So, an adequate quantity of water must be available to meet the peak demand. To meet all the fluctuations, the supply pipes, service reservoir and distribution pipes must be properly proportioned. The water is supplied by pumping directly and the pumps and distribution system must be designed to meet the peak demand. The effect of monthly variation influences the design of storage reservoir and the hourly variations influences the design of pumps and service reservoir. As the population decreases, the fluctuation rate increases.

Maximum daily demand = 1.8 x average daily demand

Maximum hourly demand of maximum day i.e. Peak demand

= 1.5 x average hourly demand
= 1.5 x Maximum daily demand/24
= 1.5 x (1.8 x average daily demand)/24
= 2.7 x average daily demand/24
= 2.7 x annual average hourly demand

COMPONENTS:
  • DOMES: 

A dome may be defined as a thin shell generated by the revolution of a regular curve about one of its axes. The shape of the dome depends on the type of the curve and the direction of the axis of revolution. In spherical and conical domes, surface is described by revolving an arc of a circle. The centre of the circle may be on the axis of rotation (spherical dome) or outside the axis (conical dome). Both types may or may not have a symmetrical lantern opening through the top. The edge of the shell around its base is usually provided with edge member cast integrally with the shell. 
Domes are used in variety of structures, as in the roof of circular areas, in circular tanks, in hangers, exhibition halls, auditoriums, Planetorium and bottom of tanks, bins and bunkers. 
Domes may be constructed of masonry, steel, timber and reinforced concrete. However, reinforced domes are more common nowadays since they can be constructed over large spans Membrane theory for analysis of shells of revolution can be developed neglecting effect of bending moment, twisting moment and shear and assuming that the loads are carried wholly by axial stresses. This however applies at points of shell which are removed some distance away from the discontinuous edge. At the edges, the results thus obtained may be indicated but are not accurate. 
The reinforcement is provided in the middle of the thickness of the dome shell near the edges usually some ring beam is provided for taking the horizontal component of the meridian stress. Some bending moment develops in the shell near the edges. Reinforcements near the top as well as near the bottom face of the shell are also provided.
  • RING BEAM: 

The size of the ring beam is obtained on basis of the hoop tension developed in the ring due to the horizontal component of the meridian stress. The concrete area is obtained so that the resulting tensile stress when concrete alone is considered does not exceed 1.1 N/mm2 to 1.70 N/mm2 for direct tension and 1.5 N/mm2 to 2.40 N/mm2 for tension due to bending in liquid resisting structure depending on the grade of concrete. Reinforcement for the hoop stress is also provided with the allowable stress in steel as 115 N/mm2 (or 150 N/mm2) in case of liquid retaining structures and 140 N/mm2 (or 190 N/ mm2) in other cases. The ring should be provided so that the central line of the shell passes through the centroid of the ring beam. Reinforcement has to be provided in both the directions. If the reinforcement along the meridians is continued up to the crown, there will be congestion of steel there. Hence, from practical considerations, the reinforcement along the meridian is stopped below the crown and a separate mesh is provided. In case of domes with lantern opening with concentrated load acting there, ring beam has to be provided at the periphery of the opening. The edge beam there will, however, be subjected to hoop compression in place of hoop tension.


  • OVERHEAD WATER TANK AND TOWERS: 

(1) Overhead water tanks of various shapes can be used as service reservoir as a balancing tank in water supply schemes and for replenishing the tanks for various purposes.

(2) Reinforced concrete water towers have distinct advantages as they are not affected by climatic changes, are leak proof, provide greater rigidity and are adoptable for all shapes.

(3) Side walls

(4) Floors., beams, including circular girder

(5) Bracing and

(6) Foundations

  • FLOORS:

(I) Floors of Tanks Resting on Ground.

If the tank is resting directly over ground, floor may be constructed of concrete with nominal percentage of reinforcement provided that it is certain that the ground will carry the load without appreciable subsidence in any part and that the concrete floor is cast in panels with sides not more than 4.5m with contraction or expansion joints between. In such cases a screed or concrete layer less than 75mm thick shall first be placed on the ground and covered with a sliding layer of bitumen paper or other suitable material to destroy the bond between the screed and floor concrete. In normal circumstances the screed layer shall be of grade not weaker than M 10,where injurious soils or aggressive water are expected, the screed layer shall be of grade not weaker than M 15 and if necessary a sulphate resisting or other special cement should be used.

(II) Floor of Tanks Resting on Supports

(a) If the tank is supported on walls or other similar supports the floor slab shall be designed as floor in buildings for bending moments due to water load and self-weight.

(b) When the floor is rigidly connected to the walls (as is generally the case) the bending moments at the junction between the walls and floors shall be taken into account in the design of floor together with any direct forces transferred to the floor from the walls or from the floor to the wall due to suspension of the floor from the wall. If the walls are non-monolithic with the floor slab, such as in cases, where movement joints have been provided between the floor slabs and walls, the floor shall be designed only for the vertical loads on the floor.

(c) In continuous T-beams and L-beams with ribs on the side remote from the liquid, the tension in concrete on the liquid side at the face of the supports shall not exceed the permissible stresses for controlling cracks in concrete. The width of the slab shall be determined in usual manner for calculation of the resistance to cracking of T-beam, L beam sections at supports.

(d) The floor slab may be suitably tied to the walls by rods properly embedded in both the slab and the walls. In such cases no separate beam (curved or straight) is necessary under the wall, provided the wall of the tank itself is designed to act as a beam over the supports under it.

(e) Sometimes it may be economical to provide the floors of circular tanks, in the shape of dome. In such cases the dome shall be designed for the vertical loads of the liquid over it and the ratio of its rise to its diameter shall be so adjusted that the stresses in the dome are, as far as possible, wholly compressive. The dome shall be supported at its bottom on the ring beam which shall be designed for resultant circumferential tension in addition to vertical loads.

  • WALLS: 

(I) Provision of Joints

(a) Where it is desired to allow the walls to expand or contract separately from the floor, or to prevent moments at the base of the wall owing to fixity to the floor, sliding joints may be employed.

(b) The spacing of vertical movement joints should be the majority of these joints may be of the partial or complete contraction type, sufficient joints of the expansion type should be provided to satisfy the requirements.

(II) Pressure on Walls.

(a) In liquid retaining structures with fixed or floating covers the gas pressure developed above liquid surface shall be added to the liquid pressure.

(b) When the wall of liquid retaining structure is built in ground, or has earth embanked against it, the effect of earth pressure shall be taken into account.

(III) Walls or Tanks Rectangular or Polygonal in Plan. While designing the walls of rectangular or polygonal concrete tanks, the following points should be borne in mind.

(a) In plane walls, the liquid pressure is resisted by both vertical and horizontal bending moments. An estimate should be made of the proportion of the pressure resisted by bending moments in the vertical and horizontal planes. The direct horizontal tension caused by the direct pull due to water pressure on the end walls, should be added to that resulting from horizontal bending moments.

(b) On liquid retaining faces, the tensile stresses due to the combination of direct horizontal tension and bending action shall satisfy the following condition:

(t./t )+ ( óc t . /óc t) ≤ 1           ………………………………………….(I)
t. = calculated direct tensile stress in concrete
t = permissible direct tensile stress in concrete
óc t = calculated tensile stress due to bending in concrete.
óc t = permissible tensile stress due to bending in concrete.

(c) In the case of rectangular or polygonal tanks, the side walls act as two way slabs, whereby the wall is continued or restrained in the horizontal direction, fixed or hinged at the bottom and hinged or free at the top. The walls thus act as thin plate subjected triangular loading and with boundary conditions varying between full restraint and free edge. The analysis of moment and forces may be made on the basis of any recognized method.

(d) At the vertical edges where the walls of a reservoir are rigidly joined, horizontal reinforcement and haunch bars should be provided to resist the horizontal bending moments even if the walls are designed to withstand the whole load as vertical beams or cantilever without lateral supports.


(IV) Walls of Cylindrical Tanks.

While designing walls of cylindrical tanks the following points should be borne in mind:

(a) Walls of cylindrical tanks are either cast monolithically with the base or are set in grooves and key ways (movement joints). In either case deformation of wall under influence of liquid pressure is restricted at and above the base. Consequently, only part of the triangular hydrostatic load will be carried by ring tension and part of the load at bottom will be supported by cantilever action.


(b) It is difficult to restrict rotation or settlement of the base slab and it is advisable to provide vertical reinforcement as if the walls were fully fixed at the base, in addition to the reinforcement required to resist horizontal ring tension for hinged at base, conditions of walls, unless the appropriate amount of fixity at the base is established by analysis with due consideration to the dimensions of the base slab the type of joint between the wall and slab, and , where applicable, the type of soil supporting the base slab.

  • ROOFS:

(I) Provision of Movement Joints.

To avoid the possibility of sympathetic cracking it is important to ensure that movement joints in the roof correspond with those in the walls, if roof and walls are monolithic. It, however, provision is made by means of a sliding joint for movement between the roof and the wall correspondence of joints is not so important.

(II) Loading.

Field covers. of liquid retaining structures should be designed for gravity loads, such as the weight of roof slab, earth cover if any, live loads and mechanical equipment. They should also be designed for upward load if the liquid retaining structure is subjected to internal gas pressure. A superficial load sufficient to ensure safety with the unequal intensity of loading which occurs. during the placing of the earth cover should be allowed for in designing roofs. The engineer should specify a loading under these temporary conditions which should not be exceeded. In designing the roof, allowance should be made for the temporary condition of some spans loaded and other spans unloaded, even though in the final state the load may be small and evenly distributed.

(III) Water Tightness
In case of tanks intended for the storage of water for domestic purpose, the roof must be made water-tight. This may be achieved by limiting the stresses as for the rest of the tank, or by the use of the covering of the waterproof membrane or by providing slopes to ensure adequate drainage.

(IV)Protection against Corrosion:
Protection measure shall be provided to the under-side of the roof to prevent it from corrosion due to condensation.

(V) Minimum Reinforcement:

(a) The minimum reinforcement in walls, floors and roofs in each of two directions at right angles shall have an area of 0.3 per cent of the concrete section in that direction for sections up to 100mm, thickness. For sections of thickness greater than 100mm, and less than 450mm the minimum reinforcement in each of the two directions shall be linearly reduced from 0.3 percent for 100mm thick section to 0.2 percent for 450mm, thick sections. For sections of thickness greater than 450mm, minimum reinforcement in each of the two directions shall be kept at 0.2 per cent. In concrete sections of thickness 225mm or greater, two layers of reinforcement steel shall be placed one near each face of the section to make up the minimum reinforcement.

(b) In special circumstances floor slabs may be constructed with percentage of reinforcement less than specified above. In no case the percentage of reinforcement in any member be less than 0.15% of gross sectional area of the member.


(VI) Minimum Cover to Reinforcement:

(a) For liquid faces of parts of members either in contact with the liquid (such as inner faces or roof slab) the minimum cover to all reinforcement should be 25mm or the diameter of the main bar whichever is greater. In the presence of the sea water and soils and water of corrosive characters the cover should be increased by 12mm but this
Additional cover shall not be taken into account for design calculations.

(b) For faces away from liquid and for parts of the structure neither in contact with the liquid on any face, nor enclosing the space above the liquid, the cover shall be as for ordinary concrete member.

DESIGN OF INTZE WATER TANK

DESIGN CRITERIA:

Water Quantity Estimation:

The quantity of water required for municipal uses for which the water supply scheme has to be designed requires following data:
Water consumption rate (Per Capita Demand in liters per day per head) Population to be served.
Quantity = Per capita demand x Population

Water Consumption Rate

It is very difficult to precisely assess the quantity of water demanded by the public, since there are many variable factors affecting water consumption. The various types of water demands, which a city may have, may be broken into following class


 Table - Water Consumption for Various Purposes:

S.NO.
  Types of Consumption
  Normal Range
   (lit./capita/day)
 Average
  % Share
   1
Domestic Consumption
       65-300 
      160
   35
   2
Industrial and Commercial
Demand
       45-450
      135
   30
   3
Public including Fire Demand
Uses
       20-90
       45
   10
   4
Losses and Waste
       45-150
       62
   25


Fire Fighting Demand:

The per capita fire demand is very less on an average basis but the rate at which the water is required is very large. The rate of fire demand is sometimes treated as a function of population and is worked out from following empirical formula:

Table 3.2 - Empirical Formula

S.NO.
  Authority
    Formula (P in thousand)
   Q for (1 lakh
    Population)
     1
American
Insurance
Association
Q (L/min)=4637 ÖP (1-0.01 ÖP)
           41760
     2
Kuchling's
Formula
Q (L/min)=3182 ÖP
           31800
     3
Freeman's
Formula
Q (L/min)= 1136.5(P/5+10)
           35050
     4
Ministry of
Urban
Development
Manual Formula
Q (kilo liters./d)=100 ÖP for P>50000
           31623

 Design Periods & Population Forecast:

This quantity should be worked out with due provision for the estimated requirements of the future. The future period for which a provision is made in the water supply scheme is known as the design period.  

Design period is estimated based on the following: 
• Useful life of the component, considering obsolescence, wear, tear, etc. 
• Expand-ability aspect. 
• Anticipated rate of growth of population, including industrial, commercial developments &     migration-immigration. 
• Available resources. 
• Performance of the system during initial period.  

Population Forecasting Methods:

The various methods adopted for estimating future populations are given below. The particular method to be adopted for a particular case or for a particular city depends largely on the factors discussed in the methods, and the selection is left to the discretion and intelligence of the designer. 
  1. Incremental Increase Method 
  2. Decreasing Rate of Growth Method 
  3. Simple Graphical Method 
  4. Comparative Graphical Method 
  5. Ratio Method 
  6. Logistic Curve Method 
  7. Arithmetic Increase Method
  8. Geometric Increase Method. 

DESIGN CRITERIA OF CONCRETE (I. S. I):


In water retaining structure a dense impermeable concrete is required therefore, proportion of fine and course aggregates to cement should be such as to give high quality concrete. Concrete mix weaker than M20 is not used. The minimum quantity of cement in the concrete mix shall be not less than 30 KN/m3.The design of the concrete mix shall be such that the resultant concrete issue efficiently impervious. Efficient compaction preferably by vibration is essential. The permeability of the thoroughly compacted concrete is dependent on water cement ratio. Increase in water cement ratio increases permeability, while concrete with low water cement ratio is difficult to compact. Other causes of leakage in concrete are defects such as segregation and honey combing. All joints should be made water-tight as these are potential sources of leakage. Design of liquid retaining structure is different from ordinary R.C.C, structures as it requires that concrete should not crack and hence tensile stresses in concrete should be within permissible limits. A reinforced concrete member of liquid retaining structure is designed on the usual principles ignoring tensile resistance of concrete in bending. Additionally it should be ensured that tensile stress on the liquid retaining ace of the equivalent concrete section does not exceed the permissible tensile strength of concrete as given in table 1. For calculation purposes the cover is also taken into concrete area. Cracking may be caused due to restraint to shrinkage, expansion and contraction of concrete due to temperature or shrinkage and swelling due to moisture effects. Such restraint may be caused by.  

i. The interaction between reinforcement and concrete during shrinkage due to drying. 
ii. The boundary conditions. 
iii. The differential conditions prevailing through the large thickness of massive concrete Use of small size bars placed properly, leads to closer cracks but of smaller width. The risk of cracking due to temperature and shrinkage effects may be minimized by limiting the changes in moisture content and temperature to which the structure as a whole is subjected. The risk of cracking can also be minimized by reducing the restraint on the free expansion of the structure with long walls or slab founded at or below ground level, restraint can be minimized by the provision of a sliding layer. This can be provided by founding the structure on a flat layer of concrete with interposition of some material to break the bond and facilitate movement. In case length of structure is large it should be subdivided into suitable lengths separated by movement joints, especially where sections are changed the movement joints should be provided. Where structures have to store hot liquids, stresses caused by difference in temperature between inside and outside of the reservoir should be taken into account. The coefficient of expansion due to temperature change is taken as 11 x 10-6 /° C and coefficient of shrinkage may be taken as 450 x 10-6 for initial shrinkage and 200 x 10-6 for drying shrinkage.

GENERAL DESIGN REQUIREMENTS (I.S.I):

Plain Concrete Structures:

Plain concrete member of reinforced concrete liquid retaining structure may be designed against structural failure by allowing tension in plain concrete as per the permissible limits for tension in bending. This will automatically take care of failure due to cracking. However, nominal reinforcement shall be provided, for plain concrete structural members.  

No comments:

Post a Comment